Teal‎‎‎ Park Site‎‎ Strip

Client

Taylor Lindsey

Contract Particulars

Teal Park – Site Strip, Haulage and Site Fill

Contract Value

£150k

Contract Duration

6 Weeks

Contract Overview

Works involved full site topographical survey, 3d Modelling of cut & fill, 12,500m2 topsoil strip and removal for recycling.

Then under the MMP we loaded and hauled 9000m3 of suitable engineered fill from several local client sites and levelled, compacted and trimmed to required level under the close supervision of the earthworks engineer & testing team. Final testing was then undertaken to confirm a suitable CBR had been achieved on the final layer.

The entire project was carried out with all plant, operators, haulage and engineers being directly employed/owned by the DC group.