Travis Perkins

Client

Taylor Lindsey

Contract Particulars

Construction of New Portal Frame Building & Service Yard

Contract Value

£2.2m

Contract Duration

36 Weeks

Contract Overview

Works Included mass fill, strip and pad foundations, Internal & external drainage, internal power floated floor slab, precast concrete retaining wall, large external concrete yard (brush finish), fencing and gates.

Principle contractor role including liaising with the client’s sub-contractors. 

Works were completed and handed over on time and within budget.